2014 Spring Meeting & 10th Global Congress on Process Safety

(152a) Ethylene Plant Operations with Chevron Phillips Chemical Company LP Back End E-Series(R) Catalyst

Authors

Khan, M. - Presenter, Chevron Phillips Chemical LP
Nill, J. L., Chevron Phillips Chemical Company, LP

ETHYLENE PLANT OPERATIONS
WITH CHEVRON PHILLIPS CHEMICAL COMPANY LP BACK END E-SERIES®
CATALYST

Manzoor Khan,
Operations Engineer, Chevron Phillips Chemical Company LP

Jennifer Nill,
E-Series® Catalyst Americas Technical Sales Manager, Chevron
Phillips Chemical Company LP

This
paper will discuss the most recent operating data with the E-Series®
catalyst in Chevron Phillips Chemical's Port Arthur, Texas Plant. The Port
Arthur plant operates Back End acetylene hydrogenation reactors. With constant
selectivity throughout the run, the catalyst has achieved greater than 24
months of run length without regeneration. This has improved plant ethylene
production rates and reliability.