Hence, the facility siting study should not be seen as the final answer that the facility must conform to without looking further. The study can instead be viewed as a conservative screening tool that will identify critical hazard areas in the facility arrangement, processes and building construction. The path forward from facility siting could include advanced analysis techniques, passive mitigation measures, active mitigation measures and then building retrofits. This approach focuses on accurately determining the hazard and minimizing it before designing and structural upgrades for existing buildings or new structures. This approach can result in fewer buildings requiring retrofit and less extensive building retrofits for those in need.