- Implementing a Risk-Based MOC Program for Upstream Assets
At Pan American Energy LLC (PAE), one of the Golden Rules as well as one of the pillar of the Integrity Management Procedure is "Management of Change" that states: For work involving changes either temporary, permanent or emergency in the organization, personnel, systems, processes, procedures, equipment, products, materials or substances and rules and regulations, it requires a Management of Change Process” which must include:
- A Risk Assessment performed by all those who are affected by the change.
- The development of a Work Plan to specify clearly any control measure to be implemented in relation to:
- The authorization of the work plan issued by staff responsible.
The challenge was to implement a procedure in an organization of this size, that it was not easy to implement, and in which we raised questions with regard to re-order the operational structure for personnel to carry out the management of change process, as to generate simple records for the management of these changes, define approval process, define the Risk Matrix and the responsible according to the risk of the requested change, among other doubts.
This paper presents the challenges we faced and how through the use of a simple documentation for change management (Notes of Change), personnel reorganization, changes of paradigms and culture change in the organization and a very well designed process for registration through the Management of Change of Facilities (GMI) method, allowed us to identify, appraise, approve, manage and document changes either temporary or permanent, operational, technological, of facilities and equipment to keep mechanical integrity and process safety under control in the operation. We were able to apply a successful process for Management of Change that works and that is business as usual now.
Some changes requiring the implementation of the GMI method and for which Notes of Change were created include but are not limited by these requirements: